Some highlights from the lab this summer. We had a crew of three high school interns: Vincent, Maya, and Sam. Vincent was exploring ice sliding on different rock types. Maya used active acoustics to characterize two ice interfaces at different normal stress. Sam used bench top test of carbon mineralization while looking at the effect of stress and pH. They were a great crew!
text
Friday, 1 September 2023
Summer 2023 in the lab
Friday, 23 June 2023
Introducing "PinQ": our new cryogenic forced oscillation apparatus
With our funding of a study on the dislocation and strain dependence of attenuation (also called inverse Q) and the arrival of Dr. Hatsuki Yamauchi to work on the project, we decided to assess our machine capabilities. It became quite clear that our original idea of using the biax would not be a good idea because it is not stiff enough (which is part of why it is a great friction apparatus). So we needed to create a new apparatus. Yamauchi-san and I had both worked on a great apparatus in Japan, that had high strain resolution and very precise application of stress. That apparatus ran at room temperature or slightly higher temperatures. So we needed to adapt that design (the "TKY-style" apparatus) for cold temperature work.
2021 and 2022 were bad times for purchasing parts and it seemed every component was on back order and seriously delayed. The machinist also had a back log. Whatever could be done by us, we did.
First big task was to find a nice stiff, hopefully pre-existing, frame. Ted found one (as he does) but it was looking very dirty and not the right color at all. Hatsuki suggested a paint job and new color scheme. And thus the frame was painted a bright beautiful shade of pink.
Eventually the laser displacements meters (and their stage motors), the screw jack, the stepper motor, the piezo-electric actuator and the rotational base all arrived and Hatsuki assembled it all on the stone table Ted had acquired from somewhere.
Friday, 12 February 2021
Tether testing with Vishaal
Tuesday, 1 September 2020
Final Install on the AutoLab
This week the guys from New England Research (NER) came out to do the final install on our AutoLab2000 HPHT. The biggest task was to get that big pressure cell, which has been sitting in a big crate in the middle of the prep room for a few months, into the rig.
Not an easy feat. They decided to use the multi-ton overhead crane in the main lab. Eyebolts on the top of the pressure cell made it easy to lift.
Monday, 10 August 2020
It moved!
A lot has progressed in the lab since we first started ramping back up in early July. One major development is that we moved the ice rig. Step one was to disconnect all of the wiring and hydraulics from the frame.
Meanwhile, Jake and Ted were back in the new lab, prepping the anti-vibration table, making sure it was perfectly horizontal and up against the back wall.
Monday, 11 May 2020
New Walk In
Before the lockdown, we were *this close* to getting our own walk in freezer set up. It will also be housed in the Instruments building, so no more walking across campus in the rain with samples. A room in the back corner of the warehouse was cleared out and the floor given a nice paint job. That's gray with specks of different shades of blue. We taped off the location for the walk in and awaited its arrival from culinary depot. It arrived stacked nicely on a pallet and the refrigeration team went ahead with installation.

I walked away late morning to attend a meeting and by the time I returned it was already assembled. They were so fast!
Tuesday, 14 April 2020
Extreme makeover gets even more extreme: Part 2, the prep room

First task was to break down everything metal, clean it, sand it and paint it black. Starting to look good.